Data centers are turning to old jet engines as the wait for power grows

ID
42739
Status
summarized
Published
04 Nov 2026, 6:19 AM
Fetched
04 Nov 2026, 7:49 AM
Provider
TechCrunch
Category
technology
Original URL
https://techcrunch.com/2026/11/03/data-centers-are-turning-to-old-jet-engines-as-the-wait-for-power-grows/
Source URL
https://techcrunch.com/feed/

Summary

Score
6.5
Created
04 Nov 2026, 7:50 AM
Tags
Audience
developersai_ml_learnerssaas_founders

What happened

Some AI data centers are converting retired jet engines to burn natural gas because grid connections and new turbines take years; Rystad Energy analyst Audun Martinsen says jet-powered units can get a data center running in 24 months, while a 100MW grid hookup in Northern Virginia takes about seven years. xAI has installed eight converted jet-engine turbines in Mississippi for its Colossus 2 data center in Memphis, and Microsoft pulled out as anchor customer for Nscale's Loughton, England site after the utility said power would not arrive until the early-to-mid 2030s.

Why it matters

If you are choosing AI cloud/GPU capacity or planning a data-center-dependent product, ask for power delivery dates, not just announced capacity: the article contrasts 24 months for converted jet engines with roughly seven years for 100MW in Northern Virginia, and shows an anchor customer walking after a utility delay to the early-to-mid 2030s. For Malaysian founders evaluating regional AI infrastructure partners, announced data centers are not the same as energized capacity.

Discussion angle

What evidence should a Malaysian team demand from an AI cloud or GPU provider to prove it has energized capacity—power delivery dates, utility contracts, on-site generation—rather than just announced data-center plans?